I am trying to automate a case due date process for one of our teams. They have requested that the "Requested Completion Date" be 2 days before the Latest Completion Date field.

Is it as simple as inserting the 'Latest Completion Date' field and just '-2' in the formula? I'm not quite sure how to use the formulas on a specific field and base the update on that field date. 

Is this possible? 

Best Answer chosen by Manmeet Dosanjh
Amnon KruviAmnon Kruvi
Hi Manmeet,

If someone manually fills in the Latest Completion Date, and you just want to set the field to be 2 days before that? Then yeah - just adding -2 after the field in a formula will go back 2 calendar days.

All Answers

Amnon KruviAmnon Kruvi
Hi Manmeet,

If someone manually fills in the Latest Completion Date, and you just want to set the field to be 2 days before that? Then yeah - just adding -2 after the field in a formula will go back 2 calendar days.
This was selected as the best answer
Manmeet DosanjhManmeet Dosanjh
Thanks! Just wanted to make sure that would work. 
Sunil Kumar SirangiSunil Kumar Sirangi
Hi Manmeet,

Will the "Requested Completion Date" field value be always 2 days before the "Latest Completion Date" field. If yes you can create the "Requested Completion Date" field as a formula field and value should be as below.
Latest_Completion_Date__c - 2

If it is already a date field and somehow cannot be changed to formula, you can use workflow rule to check if "Latest Completion Date" value is changed using the formula
 
ISCHANGED(Latest_Completion_Date__c)

Once it is true you can use the above formula(Latest_Completion_Date__c - 2) as the field update value.

Thanks. 

 
sakshi nagpalsakshi nagpal
Hi Manmeet,

 if  you are using date type field , then it is as simple as -2

 Thanks
Manmeet DosanjhManmeet Dosanjh

Thanks Sunil!


I'm still trying to figure out the best method on solving this for the team. They're basically wanting a better method of due dates and priorities. 

Ideally, since we have an SLA of 3-5 days on requests, that most of our cases would have the Requested date = Latest Date - 2

 

But there are instances where a request comes in Monday, with latest due date of Tuesday. These are not common but do happen. 

All the while, I need to also update the priority. So that it starts off as Low but if Requested Date = Latest Date - 1, Priority = Medium. If Requested Date = Latest Date, Priority = High.

This is overly complicated so I'm not sure I will do this for them but thought I'd try at least. 

Amnon KruviAmnon Kruvi
If you want to give it a shot, we'll be happy to help you implement the priority as well. You could use a time-based workflow or process, for example, to automatically change the priority to Normal or High 1 and 2 days before the due date.
Manmeet DosanjhManmeet Dosanjh
Ahh I see, that should work! Thanks for the quick reply.